TROJA BRIDGE
The "Trojská lávka" project in cooperation with the company MCE Slaný s.r.o. provided one of the options for using the PMSS system.
Three PMSS pontoon modules with a total load of 108 tons were used to transport the steel structure of the bridge across the Vltava River from the city area of Troja to the Císářský Island. The weight of the steel structure, including the supporting structures, was 94 tons.
It was a coordinated move utilizing the PMSS system and a Liebherr LTR 1100 crawler crane.